Concrete Calculator

Calculate concrete volume for slabs, footings and columns, with cement, sand and aggregate quantities.

Please note: Material estimates for planning only. Always confirm quantities against your drawings, local building codes and supplier specifications before ordering. Structural work requires a qualified engineer.

What the Concrete Calculator does

Concrete volume is length by width by thickness for a slab, or the cross-section by height for a column. Because dry cement, sand and aggregate occupy more space than the mixed concrete they produce, the dry quantities are scaled up by roughly 54% before splitting them by the mix ratio.

Formula

  • Slab volume = Length × Width × Thickness
  • Circular volume = π × (Diameter ÷ 2)² × Height
  • Order volume = Net volume × (1 + Waste %)
  • Dry volume = Order volume × 1.54, split by the mix ratio
  • Cement bags = Dry cement volume × 1,440 kg/m³ ÷ Bag size

Inputs explained

InputUnitRequiredNotes
Elementone of 4 optionsYes
LengthnumberIn some modesFor steps, this is the tread depth of one step. Accepts more than 0. Shown in 3 of the 4 modes.
Length unitone of 6 optionsIn some modesShown in 3 of the 4 modes.
WidthnumberIn some modesAccepts more than 0. Shown in 3 of the 4 modes.
Width unitone of 6 optionsIn some modesShown in 3 of the 4 modes.
Thickness or depthnumberIn some modesFor steps, this is the rise of one step. Accepts more than 0. Shown Element is Slab or footing (rectangular), or Element is Steps.
Thickness or depth unitone of 5 optionsIn some modesShown Element is Slab or footing (rectangular), or Element is Steps.
DiameternumberIn some modesAccepts more than 0. Shown Element is Circular column or pier.
Diameter unitone of 5 optionsIn some modesShown Element is Circular column or pier.
HeightnumberIn some modesAccepts more than 0. Shown Element is Column (rectangular), or Element is Circular column or pier.
Height unitone of 6 optionsIn some modesShown Element is Column (rectangular), or Element is Circular column or pier.
Number of elementsnumberYesAccepts 1 or more.
Number of stepsnumberIn some modesAccepts 1 or more. Shown Element is Steps.
Concrete mixone of 4 optionsYes
Waste allowance%YesExtra material for cuts, breakage and offcuts. 5–10% is typical, more for complex layouts.
Cement bag sizekgYesAccepts 1 or more.
Ready-mix price per m³selected currencyOptionalAccepts 0 or more.
Currencyone of 10 optionsOptional

How to use it

  1. Choose Element and Concrete mix.
  2. Enter Number of elements, Waste allowance and Cement bag size.
  3. Fill in the remaining inputs the form shows for your choice.
  4. Optionally add Ready-mix price per m³.
  5. Select Calculate.

Worked example

A 5 m × 4 m slab, 100 mm thick, M20 mix (1:1.5:3), 10% waste, 50 kg bags.

Length
5 m
Width
4 m
Thickness
100 mm
Mix
1:1.5:3
Waste
10

Net 2 m³, order 2.2 m³. Dry volume 3.388 m³ → cement 0.616 m³ = 887 kg = 18 bags, sand 0.924 m³, aggregate 1.848 m³.

Frequently asked questions

Why is the dry volume larger than the concrete volume?

Dry sand and aggregate contain air voids that fill with cement paste and water during mixing. The 1.54 factor is the standard allowance for that compaction.

How much waste should I allow?

5–10% for a simple slab. Increase it for complex shapes, pump losses, or uneven subgrade that soaks up extra depth.

Should I mix on site or order ready-mix?

Below roughly 1 m³ site mixing is usually practical. Above that, ready-mix is cheaper, faster and far more consistent.